Posted on: October 27, 2022

[ARCHIVED] Eagle Bay Community Park development on track for spring opening

an 3-D rendering of the layout for the Eagle Bay Community Park including playground and sport court

Construction has resumed on the Eagle Bay Community Park project this fall and will start up again as soon as weather conditions allow to get the much-anticipated park to completion in spring 2023.

Unforeseen challenges with drainage and geotechnical concerns with soil conditions, protection of the septic field and elevations, particularly for the planned sport court area prompted the need for some redesigning of the park plan.

“While it was disappointing to have these delays, it is far better to ensure we get the sport court properly sited and built with appropriate drainage so it can sustain long-term use,” says Ryan Nitchie, the CSRD’s Team Leader of Community Services. “The changes we have made will maintain nearly all the elements of the previous design, except for the nature-play area − that area will now become an expanded lawn space.”

Eagle Bay Community Park will feature a children’s playground with accessible play components including a pour-in-place, rubberized fall zone around the play areas, outdoor fitness equipment, multipurpose sport courts, green play spaces and a picnic shelter.

The nature play area was removed from the design to avoid potential interference with the existing septic field that serves the Eagle Bay Community Hall. An underground piping and rock pit system is also being installed at the site to prevent issues with drainage.

The additional work increased the overall budget of the project, however, Columbia Shuswap Regional District (CSRD) Board Directors approved using an additional $250,000 of Electoral Area C Community Works Funds to cover the costs. This means there will be no additional tax levy needed to support the park development.

“This project has been a success story from the beginning with the exceptional partnership with the Eagle Bay Community Hall Society to use the lands, to the enthusiastic interest from the community in helping develop the design plans, to the point now where construction is underway,” says Nitchie.

“Despite the challenges discovered when we got the shovels in the ground, we know this is going to be a tremendous community asset for public use when it opens next spring.”

Photo: A 3D rendering of the layout of a portion of Eagle Bay Community Park including a playground, sport court and picnic shelter.

View printable copy (PDF)

Facebook Twitter Email

Other News in CSRD News

A fire hydrant located in Blind Bay.

Fire hydrant servicing starts October 1

Posted on: September 28, 2023
Sorrento wall of fire

Fighting to protect Sorrento

Posted on: September 19, 2023
Resiliency Centre graphic

Resiliency Centre open in Salmon Arm

Posted on: September 11, 2023
Info Centre Volunteers

EOC Update - September 8, 2023

Posted on: September 8, 2023
Info update graphic

Service changes in the North Shuswap

Posted on: September 7, 2023
Scotch Creek Transfer

Scotch Creek Transfer Station

Posted on: September 5, 2023
Holding Road

Holding Road Access

Posted on: September 5, 2023
structure loss

Structure loss access deadline

Posted on: September 4, 2023
Gerald Foreman from Shuswap Clothing

Business community backs fire effort

Posted on: September 3, 2023
Todd and Kelly van Ruyskensvelde

Fueling the firefighters

Posted on: August 30, 2023
2023-08-30 Sorrento fire last night

Update: Sorrento fire overnight

Posted on: August 30, 2023
Loading supplies for barge

Barge Transportation Submission Form

Posted on: August 26, 2023
water station update

Sorrento Bulk Water Station Update

Posted on: August 22, 2023
What Do I Need To Know If I Am Located East of the Evacuation Alert (1)

UPDATE – August 22, 2023 at 6:00 PM

Posted on: August 20, 2023
False Information

Caution: Misinformation

Posted on: August 22, 2023
UPDATE – August 20, 2023 at 7:00 PM

UPDATE – August 20, 2023 at 7:00 PM

Posted on: August 20, 2023
A Smoke plume at Scotch Creek

BCWS planned ignition moved ahead

Posted on: August 17, 2023
a graphic of wooden block houses with wooden block people sitting on coins.

Want to offer a place to stay?

Posted on: August 17, 2023
A Smoke plume from Lee Creek on August 12, 2023.

Evacuees return home under Alert status

Posted on: August 13, 2023
Be Prepared

Be Prepared for a Wildfire Event

Posted on: August 5, 2023
Lower East Adams Lake Wildfire 08.05.2023

Lower East Adams Lake Wildfire Update

Posted on: August 5, 2023
A map of evacuation order area for Lower East Adams Lake

Evacuation Order expanded

Posted on: August 2, 2023
A map of flights for the Lower East Adams Lake wildfire.

Cooler weather limiting fire growth

Posted on: July 27, 2023
Low water at Bristow Road Boat launch

Bristow Road Boat Launch closed

Posted on: July 26, 2023
an aerial image of the Bush Creek Wildfire.

Shuswap Emergency Program update

Posted on: July 17, 2023
A graphic with a helicopter flying with a water bucket below.

Shuswap Emergency Program update

Posted on: July 12, 2023
flames climb the slope during the night at Highway 97 and Salmon River Road.

Salmon River wildfire being held

Posted on: May 31, 2023